Top quality, just in time, most economical
Telephone: +90 232 469 7063
25
March

Extension of 154 kV Ilıca GIS' s, all works has been completed and commissioned. 21.05.2018

28
January

Extension of 154 kV Piyale GIS' s, all works has been completed and commissioned. 25.01.2018

25
November

154 kV Pınarhisar substation' s, all works has been completed and commissioned. 24.11.2017

15
October

Extension of 154 kV Aydın substation' s, all works has been completed and commissioned. 09.10.2016

28
July

Amasya Municipality' s, all works has been completed and commissioned. 27.07.2018

26
July

Extension of 154 kV Buca substation' s, all works has been completed and commissioned. 20.07.2017

26
June

154 kV Sarıkaya substation' s, all works has been completed and commissioned. 22.06.2016

24
June

Extension of 154 kV Buyukkarıstıran substation' s, all works has been completed and commissioned. 21.06.2016

1
January

The tender for the 154 kV Çine substation (EPC), was finalized and Inemko was entitled to sign the contract.

28
December

Extension of 154 kV Bodrım I substation' s, all works has been completed and commissioned. 25.12.2015

19
September

The tender for the extension of 154 kV Piyale gas insulated substation, was finalized and Inemko was entitled to sign the contract.

9
September

154 kV Cumhuriyet substation' s, all works has been completed and commissioned. 04.09.2015

6
May

The tender for the extension of 154 kV Ilıca gas insulated substation, was finalized and Inemko was entitled to sign the contract.

12
March

The tender for the 154 kV Pınarhisar substation (EPC), was finalized and Inemko was entitled to sign the contract.

25
February

The tender for the Amasya Municipality 1 MW Wind Power Plant (EPC) was finalized and Inemko was entitled to sign the contract.

10
January

The tender for the extension of 154 kV Buca substation, 154 kV OHL & 36 kV Busbar extension, was finalized and Inemko was entitled to sign the contract.

----
12
December

The tender for the extension of 154 kV Aydın substation’s 36 kV Busbar, was finalized and Inemko was entitled to sign the contract.

26
November

The tender for the extension of 154 kV Büyükkarıştıran substation, was finalized and Inemko was entitled to sign the contract.

30
October

Extension of 154 kV Bursa CCPP substation' s, all works has been completed and commissioned. 27.10.2014

5
October

Extension of 154 kV Egirdir substation' s, all works has been completed and commissioned. 01.10.2014

3
October

Extension of 154 kV Kıyıkoy substation' s, all works has been completed and commissioned. 01.10.2014

18
September

The tender for the 154 kV Sarıkaya WPP substation (EPC), was finalized and Inemko was entitled to sign the contract.

15
September

The tender for the extension of 154 kV Bodrum I substation, was finalized and Inemko was entitled to sign the contract.

06
May

The tender for the 154 kV Cumhuriyet substation (EPC), was finalized and Inemko was entitled to sign the contract.

25
December

The renewal of switchgear equipments and extension of Gezende HPP' s, all works has been completed and commissioned. 23.12.2013

13
December

Extension of 154 kV Saruhanli substation' s, all works has been completed and commissioned. 03.12.2014

13
November

The tender for the extension of 154 kV Kıyıköy substation, was finalized and Inemko was entitled to sign the contract.

24
October

The tender for the extension of 154 kV Bursa CCPP substation, was finalized and Inemko was entitled to sign the contract.

23
October

The tender for the extension of 154 kV Egirdir substation, was finalized and Inemko was entitled to sign the contract.

24
September

The Tender for Gezende HPP 154 kV renewal the switchgear equipments and extension of new OHL feeders was finalized and İnemko was entitled to sign the contract.

17
July

The tender for the extension of 154 kV Saruhanli substation, was finalized and Inemko was entitled to sign the contract.